Port Edward - Replacement of Aging and Failing Watermains - Phase I
Federal contribution
$523,333
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2009
2010
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- District of Port Edward
- Construction start
- Aug 10, 2009(actual)
- Construction end
- Dec 1, 2010(actual)
Against the original forecast
- Construction start6 months lateforecast Feb 6, 2009
- Construction end8 months lateforecast Mar 31, 2010
Also in Port Edward
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22334 in the federal list. How to read these figures.