Lagoon Expansion
Federal contribution
$145,333
Federal share33%
of $436.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
2009201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Gull Lake
- Construction start
- May 8, 2011(actual)
- Construction end
- Sep 24, 2012(actual)
Against the original forecast
- Construction start2 years lateforecast May 1, 2009
- Construction end3 months earlyforecast Dec 31, 2012
Also in Gull Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22348 in the federal list. How to read these figures.