Brooklyn Sewer & Water - Phase IV
Federal contribution
$168,088
Federal share33%
of $504.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 7, 2008
20092010
Built
Approved 7 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Regional Municipality of Queens
- Construction start
- May 11, 2009(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction end15 months earlyforecast Mar 31, 2011
Also in Liverpool