Clay Capping & Reconstruction of Road
Federal contribution
$114,967
Federal share33%
of $344.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Arm River
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Aug 30, 2010(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2009
- Construction end19 months earlyforecast Mar 31, 2012
Also in Davidson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22464 in the federal list. How to read these figures.