Water Treatment Plant Renewal

Morse, Saskatchewan

completeDrinking WaterCC
Federal contribution
$305,010
Federal share33%

of $915.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
20092010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Morse
Construction start
Jan 4, 2012(actual)
Construction end
Jan 20, 2013(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Dec 15, 2011
  • Construction end2 months earlyforecast Mar 31, 2013

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22466 in the federal list. How to read these figures.