Terrace – Skeena Industrial Development Park Intersection and Access Road

Terrace, British Columbia

completeHighways and RoadsCC
Federal contribution
$662,312
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2009
200920102011201220132014
Built

Approved 2 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Terrace
Construction start
Jun 15, 2012(actual)
Construction end
Mar 31, 2014(actual)

Against the original forecast

  • Construction start2 years lateforecast Jun 10, 2010
  • Construction end7 months earlyforecast Oct 31, 2014

Also in Terrace

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22606 in the federal list. How to read these figures.