Improvements to Existing Outfall and Primary Wastewater Treatment
Gillams, Newfoundland and Labrador
Federal contribution
$101,947
Federal share33%
of $305.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.5 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Gillams
- Construction start
- Jul 14, 2010(actual)
- Construction end
- Nov 15, 2010(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 1, 2009
- Construction end10 months lateforecast Dec 31, 2009