Back to projects

Improvements to Existing Outfall and Primary Wastewater Treatment

Gillams, Newfoundland and Labrador

completeWastewaterMRIF
Federal contribution
$101,947
Federal share33%

of $305.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.5 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Gillams
Construction start
Jul 14, 2010(actual)
Construction end
Nov 15, 2010(actual)

Against the original forecast

  • Construction start9 months lateforecast Oct 1, 2009
  • Construction end10 months lateforecast Dec 31, 2009

Also in Gillams

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22763 in the federal list. How to read these figures.