Back to projects

Water Secure Branch

Branch, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$80,602
Federal share33%

of $241.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Branch
Construction start
Nov 15, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start13 months lateforecast Oct 15, 2009
  • Construction end21 months lateforecast Jan 31, 2010

Also in Branch