Construction of Shakespeare Wastewater Servicing
Federal contribution
$1.9M
$1,877,697
Federal share29%
of $6.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Perth East
- Construction start
- Feb 15, 2009(actual)
- Construction end
- Nov 5, 2010(actual)
Against the original forecast
- Construction end5 weeks lateforecast Sep 30, 2010
Also in Milverton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22947 in the federal list. How to read these figures.