Finding a solution for the treatment of wastewater
Federal contribution
$30,987
Federal share33%
of $93.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.1 years before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Lac-Baker
- Construction start
- May 15, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 31, 2010