Finding a solution for the treatment of wastewater

Lac-Baker, New Brunswick

completeCapacity BuildingCC Top Up
Federal contribution
$30,987
Federal share33%

of $93.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.1 years before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Lac-Baker
Construction start
May 15, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22971 in the federal list. How to read these figures.