Improvements to the Water Distribution System
Federal contribution
$668,151
Federal share43%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Local Services Board of Moose Factory Island
- Construction start
- Jun 14, 2010(actual)
- Construction end
- Sep 2, 2010(actual)
Against the original forecast
- Construction end4 months earlyforecast Dec 31, 2010