Pleasant Street Water and Sewer Renewal

Miramichi, New Brunswick

completeDrinking WaterCC
Federal contribution
$492,739
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 14, 2009
2010
Built

Approved 3 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Miramichi
Construction start
Jul 15, 2009(actual)
Construction end
Jul 27, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 1, 2009
  • Construction end9 months lateforecast Oct 31, 2009

Also in Miramichi

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23056 in the federal list. How to read these figures.