Construction of the St. Clair Regional Wastewater Treatment Plant

Mooretown, Ontario

completeWastewaterCC
Federal contribution
$10.3M
$10,316,066
Federal share33%

of $30.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of St. Clair
Construction start
Jul 15, 2009(actual)
Construction end
Mar 31, 2016(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 1, 2009
  • Construction end9 months lateforecast Jun 30, 2015