Improvements to the Water Distribution System
Federal contribution
$320,833
Federal share33%
of $962.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Renfrew
- Construction start
- May 5, 2010(actual)
- Construction end
- Nov 11, 2010(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2009
- Construction end6 weeks lateforecast Sep 30, 2010
Also in Renfrew
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23079 in the federal list. How to read these figures.