Back to projects

Construction of the Amherstburg Multi-Use Recreation Complex

Amherstburg, Ontario

completeRecreationCC
Federal contribution
$7.8M
$7,835,454
Federal share33%

of $23.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 27, 2009
200920102011201220132014
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Amherstburg
Construction start
Sep 9, 2009(actual)
Construction end
Mar 31, 2014(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Sep 24, 2009
  • Construction end5 months earlyforecast Aug 15, 2014

Also in Amherstburg