Replacement of the Smithfield Overhead Bridge
Federal contribution
$2.4M
$2,365,833
Federal share28%
of $8.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Quinte West
- Construction start
- May 15, 2009(actual)
- Construction end
- Jun 11, 2010(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 29, 2009
- Construction end7 weeks earlyforecast Jul 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23113 in the federal list. How to read these figures.