Back to projects

Replacement of the Smithfield Overhead Bridge

Trenton, Ontario

completeHighways and RoadsCC
Federal contribution
$2.4M
$2,365,833
Federal share28%

of $8.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Quinte West
Construction start
May 15, 2009(actual)
Construction end
Jun 11, 2010(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Jun 29, 2009
  • Construction end7 weeks earlyforecast Jul 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23113 in the federal list. How to read these figures.