Back to projects

Remediation of Trout Lake Waste Transfer and Recycling Facility

Thunder Bay, Ontario

completeSolid Waste ManagementCC
Federal contribution
$215,339
Federal share45%

of $478.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Construction start
Aug 9, 2009(actual)
Construction end
Feb 1, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2009
  • Construction end3 months lateforecast Oct 31, 2009

Also in Thunder Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23117 in the federal list. How to read these figures.