Remediation of Trout Lake Waste Transfer and Recycling Facility
Federal contribution
$215,339
Federal share45%
of $478.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Local Services Board of Lappe
- Construction start
- Aug 9, 2009(actual)
- Construction end
- Feb 1, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 1, 2009
- Construction end3 months lateforecast Oct 31, 2009
Also in Thunder Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23117 in the federal list. How to read these figures.