Reconstruction of Garnier Road

Spanish, Ontario

completeHighways and RoadsCC
Federal contribution
$386,002
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Spanish
Construction start
May 1, 2009(actual)
Construction end
Oct 31, 2012(actual)

Against the original forecast

  • Construction end14 months lateforecast Aug 31, 2011

Also in Spanish

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23121 in the federal list. How to read these figures.