Reconstruction of Garnier Road
Federal contribution
$386,002
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Spanish
- Construction start
- May 1, 2009(actual)
- Construction end
- Oct 31, 2012(actual)
Against the original forecast
- Construction end14 months lateforecast Aug 31, 2011