Rehabilitation of Silver Harbour Road and Drive

Thunder Bay, Ontario

completeHighways and RoadsCC
Federal contribution
$98,104
Federal share33%

of $294.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Municipality of Shuniah
Construction start
May 1, 2009(actual)
Construction end
Oct 15, 2009(actual)

Against the original forecast

  • Construction start4 months earlyforecast Sep 4, 2009