Construction of a Multi-use Building
Federal contribution
$128,333
Federal share33%
of $385.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Casey
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Jan 22, 2010(actual)
Also in Belle Vallée