Improvements to Josephine Street Servicing and Streetscape
Federal contribution
$1.8M
$1,846,185
Federal share33%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of North Huron
- Construction start
- May 1, 2011(actual)
- Construction end
- Oct 19, 2012(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2011
- Construction end14 months earlyforecast Dec 31, 2013