Reconstruction of Pelham Street

Fonthill, Ontario

completeHighways and RoadsCC
Federal contribution
$769,018
Federal share33%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20092010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Pelham
Construction start
Sep 20, 2010(actual)
Construction end
Dec 31, 2012(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 15, 2010
  • Construction end2 years lateforecast Dec 31, 2010