Reconstruction of Bunny Trail
Federal contribution
$463,061
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Whitestone
- Construction start
- Jul 17, 2009(actual)
- Construction end
- Nov 29, 2010(actual)
Against the original forecast
- Construction end4 weeks lateforecast Oct 31, 2010