Back to projects

Reconstruction of Bunny Trail

Dunchurch, Ontario

completeHighways and RoadsCC
Federal contribution
$463,061
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Municipality of Whitestone
Construction start
Jul 17, 2009(actual)
Construction end
Nov 29, 2010(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Oct 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23173 in the federal list. How to read these figures.