Replacement of the Makobe River Bridge
Federal contribution
$129,542
Federal share33%
of $388.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of James
- Construction start
- Sep 16, 2013(actual)
- Construction end
- Oct 18, 2013(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 1, 2013
- Construction end3 weeks lateforecast Sep 30, 2013
Also in Elk Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23187 in the federal list. How to read these figures.