Construction of the Bradford West Gwillimbury Sports and Leisure Centre
Federal contribution
$8.2M
$8,241,666
Federal share33%
of $24.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Bradford West Gwillimbury
- Construction start
- Sep 1, 2009(actual)
- Construction end
- May 31, 2012(actual)
Against the original forecast
- Construction end5 months earlyforecast Oct 31, 2012
Also in Bradford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23195 in the federal list. How to read these figures.