Improvements to Wastewater Servicing in Thorndale
Federal contribution
$2.8M
$2,810,046
Federal share33%
of $8.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Thames Centre
- Construction start
- Mar 31, 2009(actual)
- Construction end
- Mar 31, 2016(actual)
Also in Dorchester