completeSolid Waste ManagementCC
Federal contribution
$1.8M
$1,841,256
Federal share33%

of $5.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Marathon
Construction start
May 25, 2015(actual)
Construction end
Mar 31, 2016(actual)

Also in Marathon