Renovation & Relocation of the Larder Lake Public Library
Federal contribution
$86,333
Federal share28%
of $305.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Larder Lake
- Construction start
- May 25, 2010(actual)
- Construction end
- Mar 28, 2011(actual)
Against the original forecast
- Construction start14 months lateforecast Apr 1, 2009
Also in Larder Lake
- Larder Lake Road Reconstruction$1.9M
- Larder Lake Road Reconstruction Project - Phase 2 Wastewater and Water$1.2M
- Larder Lake Municipal Complex$268.5K
- Larder Lake Waste Water Treatment Plant Retrofits$79.8K
- Raw sewage pump preplacement and soft start installlation for the waste water treatment plant$33.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24583 in the federal list. How to read these figures.