Reconstruction of Campbell Road

Evansville, Ontario

completeHighways and RoadsCC
Federal contribution
$191,767
Federal share33%

of $575.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20092010201120122013
Built
Program
Building Canada Fund - Communities Component
Construction start
Sep 9, 2009(actual)
Construction end
Dec 31, 2012(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2009
  • Construction end4 weeks lateforecast Nov 30, 2012

Also in Evansville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24586 in the federal list. How to read these figures.