Improvements to the Hamlet of Bourget Watermain and Roadworks

Rockland, Ontario

completeDrinking WaterCC
Federal contribution
$602,871
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Clarence-Rockland
Construction start
May 19, 2009(actual)
Construction end
Oct 30, 2010(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2010