Improvements to Twin-City Crossroads and Arthur Street West
Federal contribution
$777,719
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Oliver Paipoonge
- Construction start
- Aug 10, 2009(actual)
- Construction end
- Oct 16, 2009(actual)