Back to projects

Expansion and Rehabilitation of the Russell Sewage System

Embrun, Ontario

completeWastewaterCC
Federal contribution
$2.6M
$2,567,904
Federal share33%

of $7.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Russell
Construction start
Jul 23, 2009(actual)
Construction end
Dec 31, 2011(actual)

Against the original forecast

  • Construction end7 months lateforecast May 30, 2011

Also in Embrun

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24625 in the federal list. How to read these figures.