Upgrade of Ansonia/Hopper Loop

Iron Bridge, Ontario

completeHighways and RoadsCC
Federal contribution
$362,083
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 1, 2009(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 30, 2009
  • Construction end9 months lateforecast Sep 30, 2010

Also in Iron Bridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24656 in the federal list. How to read these figures.