Replacement of the Wall Street Waterline
Federal contribution
$69,190
Federal share33%
of $207.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Warwick
- Construction start
- Aug 24, 2009(actual)
- Construction end
- Nov 23, 2009(actual)
Against the original forecast
- Construction start6 months lateforecast Feb 13, 2009
Also in Watford