Diversion of Assiginack Landfill Waste and Capacity Retention
Federal contribution
$86,437
Federal share33%
of $259.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Assiginack
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Sep 21, 2012(actual)
Against the original forecast
- Construction end13 months lateforecast Sep 1, 2011