Improvements to Hicks Lake Road Safety

Thunder Bay, Ontario

completeHighways and RoadsCC
Federal contribution
$94,500
Federal share45%

of $210.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Construction start
Sep 5, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast Nov 23, 2009

Also in Thunder Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24689 in the federal list. How to read these figures.