Replacement of South Grimsby Road #18 Bridge
Federal contribution
$220,973
Federal share33%
of $662.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of West Lincoln
- Construction start
- Jan 4, 2010(actual)
- Construction end
- May 18, 2010(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Jul 2, 2010