Rehabilitation of Concession Road 7/8

Bowmanville, Ontario

completeHighways and RoadsCC
Federal contribution
$1.6M
$1,589,748
Federal share33%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Municipality of Clarington
Construction start
Nov 6, 2009(actual)
Construction end
Dec 31, 2015(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2016