Improvements to the Serpent River Water Distribution System
Federal contribution
$130,288
Federal share33%
of $390.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- North Shore, Township of the
- Construction start
- May 26, 2010(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction end11 months lateforecast Sep 15, 2010