Rehabilitation of Mulmur Landfill Road

Lisle, Ontario

completeHighways and RoadsCC
Federal contribution
$571,877
Federal share33%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20092010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Mulmur
Construction start
Jul 30, 2009(actual)
Construction end
Nov 16, 2012(actual)

Against the original forecast

  • Construction start2 months lateforecast May 29, 2009
  • Construction end5 months lateforecast Jun 30, 2012

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24724 in the federal list. How to read these figures.