Upgrading Creemore Sewage Plant
Federal contribution
$181,333
Federal share33%
of $544.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Clearview
- Construction start
- Aug 10, 2012(actual)
- Construction end
- Dec 19, 2012(actual)
Against the original forecast
- Construction start13 months lateforecast Jul 19, 2011