Reconstruction of Roads and Services in the South Park and Village Green Subdivisions
Federal contribution
$1.6M
$1,604,958
Federal share33%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Orangeville
- Construction start
- Aug 20, 2009(actual)
- Construction end
- Jun 28, 2013(actual)
Also in Orangeville
- Dufferin County Administration and Provincial Offences Court Addition$2.7M
- Upgrading of the Water Pollution Control Plant$2.4M
- Rehabilitation of the West Sector Reservoir$2.0M
- New Transfer Terminal and Bus Acquisition$1.0M
- Replacement of a 150 mm Cast Iron Watermain and a 200 mm Asbestos Cement Sanitary Sewer on Maple Crescent$729.4K