Back to projects

Renovation of the Cascade Road Bridge

Vermilion Bay, Ontario

completeHighways and RoadsCC
Federal contribution
$149,001
Federal share33%

of $447.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Machin
Construction start
Jul 22, 2009(actual)
Construction end
Mar 7, 2012(actual)

Against the original forecast

  • Construction start8 months earlyforecast Apr 1, 2010
  • Construction end7 months lateforecast Jul 31, 2011

Also in Vermilion Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24758 in the federal list. How to read these figures.