Renovation of the Cascade Road Bridge
Federal contribution
$149,001
Federal share33%
of $447.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Machin
- Construction start
- Jul 22, 2009(actual)
- Construction end
- Mar 7, 2012(actual)
Against the original forecast
- Construction start8 months earlyforecast Apr 1, 2010
- Construction end7 months lateforecast Jul 31, 2011
Also in Vermilion Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24758 in the federal list. How to read these figures.