Upgrading of Sheshegwaning Access Road
Federal contribution
$177,918
Federal share45%
of $395.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Local Roads Board of Robinson Township
- Construction start
- May 15, 2010(actual)
- Construction end
- Jan 31, 2011(actual)
Against the original forecast
- Construction end3 months lateforecast Oct 31, 2010