Extension of Wastewater and Road Services to Clinton Area
Federal contribution
$453,661
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Central Huron
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Jul 10, 2013(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 31, 2013