Replacement of Markdale Sewage Pumping Stations

Markdale, Ontario

completeWastewaterCC
Federal contribution
$456,625
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Construction start
Apr 28, 2011(actual)
Construction end
Nov 30, 2011(actual)

Against the original forecast

  • Construction start10 months lateforecast Jun 29, 2010