Decommissioning of the Havelock Facultative Lagoons

Havelock, Ontario

completeWastewaterCC
Federal contribution
$101,964
Federal share33%

of $305.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Construction start
Dec 1, 2010(actual)
Construction end
Feb 23, 2016(actual)

Against the original forecast

  • Construction start3 months lateforecast Sep 1, 2010
  • Construction end5 months lateforecast Sep 30, 2015

Also in Havelock

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24791 in the federal list. How to read these figures.