10th Street North Bridge Replacement

Seba Beach, Alberta

completeHighways and RoadsCC
Federal contribution
$23,333
Federal share27%

of $85.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 30, 2009
Built

Approved 2 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Jun 1, 2009(actual)
Construction end
Sep 15, 2009(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2009
  • Construction end4.5 years earlyforecast Mar 31, 2014

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24856 in the federal list. How to read these figures.