Water Treatment Plant

Whitemouth, Manitoba

completeDrinking WaterCC Top Up
Federal contribution
$1.5M
$1,493,217
Federal share30%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Aug 14, 2009(actual)
Construction end
Oct 18, 2010(actual)

Against the original forecast

  • Construction start2 years earlyforecast Aug 15, 2011
  • Construction end10 months earlyforecast Sep 1, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24904 in the federal list. How to read these figures.