Arena upgrade - Veteran

Veteran, Alberta

completeGreen EnergyCC Top Up
Federal contribution
$3,103
Federal share33%

of $9.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Veteran
Construction start
Oct 5, 2009(actual)
Construction end
Nov 30, 2009(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2009
  • Construction end3 months earlyforecast Feb 28, 2010

Also in Veteran

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24945 in the federal list. How to read these figures.